Harlow Street site build for Plugmere, a fictional EV charging operator
Milestone pipeline slide with a date and owner on each card
A milestone pipeline slide shows the few checkpoints a project must pass in order, each with the date it closes and the person who signs it off. This one tracks a kerbside charging site for Plugmere, a fictional EV charging operator, through five milestones from a signed lease to the first paid charge.
What is on the slide
- Title and site
- Five Milestones to Go Live. Plugmere kerbside chargers, Harlow Street site, 8 bays.
- Milestones 1 to 3
- Site Signed: 12 Feb, sales lead, council notified. Design Approved: 26 Mar, engineer, grid capacity OK. Permits Issued: 7 May, planner, traffic plan agreed.
- Milestones 4 and 5
- Install Complete: bays wired 18 Jun, site manager, safety test passed. Live and Billing: switch on 2 Jul, ops lead, app listing live.
- Closing band
- Twenty weeks from lease to first charge. Each card closes only when its owner signs it off.
When this is the right slide
Pick this slide when a project passes five gates in a fixed order and the audience needs the date, the owner and the closing condition of each gate on one screen.
What to swap it for
Timeline: 7 Numbered Milestones. Use the seven stage numbered timeline when there are more than five checkpoints, or when the stages need a short note each rather than three lines.
What this slide shows
The title reads Five Milestones to Go Live, and the framing line names Plugmere kerbside chargers at the Harlow Street site, 8 bays. Five cards run left to right, linked by chevrons, each with a numbered disc, a stage name and three short lines. Site Signed: signed 12 Feb, owner sales lead, council notified. Design Approved: approved 26 Mar, owner engineer, grid capacity OK. Permits Issued: issued 7 May, owner planner, traffic plan agreed. Install Complete: bays wired 18 Jun, owner site manager, safety test passed. Live and Billing: switch on 2 Jul, owner ops lead, app listing live. A filled band underneath carries a lightning icon, the headline Twenty weeks from lease to first charge and the line Each card closes only when its owner signs it off. Every card uses the same three line pattern, which is what lets the room compare gates quickly. The dates are short day and month forms so they fit on one line, and the year sits in the deck title or the speaker notes.
When this is the right slide
Use a milestone pipeline slide when a project has a handful of gates that must close in order and each needs a clear owner: a site build, a product launch, a fit out, a funding round. It works in a steering group or a client update, where people want to know where the project is and who is responsible for the next step. It is the wrong slide when the time between events matters more than the gates, because the cards are evenly spaced however long each stage takes. A timeline with dated, proportional spacing is better then. It is also the wrong slide for more than five gates on this layout, or for parallel workstreams, which a kanban or swimlane layout handles. A pipeline is also a good handover tool between teams. Sales hands the site to engineering at card one, engineering to planning at card two, and so on, and each owner can see who passes work to them and when. In a portfolio of sites, the same five cards make it easy to compare where each site is stuck, because the gates are identical.
How to adapt it
First, mark progress by filling the finished cards in a stronger colour and leaving future cards light, so the slide doubles as a status report. Second, replace the third line on each card with a risk when the audience is a risk committee, for example traffic plan objection possible. Third, reuse the same five cards for every site in a rollout and change only the dates, owners and site name, so a portfolio review can flip through sites with the same pattern each time. When dates move, update both the card and the duration in the band, and check that the band still matches the first and last dates exactly.
What makes this slide work
Each card has a date, an owner and a result
Every card repeats the same three lines: the date, the owner and the result that closes it, such as Approved 26 Mar, Owner: Engineer, Grid capacity OK. The repetition makes the slide a checklist of gates, and anyone can read across the row to see who is next.
The band answers the duration question
The closing band says twenty weeks from lease to first charge, which matches the cards: 12 February to 2 July is exactly twenty weeks. Executives get the one number they ask for, and the cards above show how it breaks down.
Numbered badges show progress
Large numbered discs from 01 to 05 head each card, linked by chevrons. In a status meeting the presenter can say the project is at 03 and the room immediately sees two gates done and three to go, without any extra progress bar.
Questions people ask
What is the difference between a milestone pipeline and a timeline slide?
A pipeline treats each milestone as a gate with conditions, an owner and a result, spaced evenly whatever the gap between dates. A timeline places events on a time scale so the spacing shows duration. Use a pipeline when the audience cares who closes each step, and a timeline when the length of each gap is the point.
How many milestones should a pipeline slide have?
Five is a good number for one slide, and this layout holds exactly five cards. Fewer than four usually means the milestones are too broad to manage; more than seven means some are tasks rather than milestones. A long project can use one pipeline per phase, each with its own five gates.
Should each milestone card name a person or a role?
A role, on a slide that will be reused. Sales lead, engineer, planner, site manager and ops lead stay correct when people change jobs, and the deck can be copied for the next site. In a weekly project meeting, adding the person's first name in the speaker notes is fine.
What goes in the band under the milestone cards?
One headline that sums up the whole pipeline and one supporting line. Here the headline is twenty weeks from lease to first charge, and the line says each card closes only when its owner signs it off. It answers the question executives ask first: how long does this take and who is accountable.
How do I show a late milestone on the pipeline?
Change that card's first line to the new date and add the slip, for example Issued 21 May, two weeks late, and say what it pushes back. Do not hide the original date. If more than one milestone slips, a timeline slide with the original and revised dates side by side is clearer.
How do I present a milestone pipeline to a steering group?
Say where the project is today, for example card three of five, then talk only about the next gate: what must be true to close it, who closes it, and what could stop them. Finish on the date in the band. Most steering groups need two minutes on this slide, not ten.
Build your own in about a minute
The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.
Make one like thisOther slide examples
Decision flowchart slide for escalating a patient complaint
A decision flowchart slide shows a process that forks, with diamond shaped questions sending the work down different paths depending on the answer. This one tells the front desk at Penvale Dental, a fictional practice, exactly when a patient complaint goes to the practice manager and when the desk resolves it.
Numbered roadmap slide with a quarter and owner per row
A numbered roadmap slide lists the stages of a plan from top to bottom in the order they happen, each with when it lands and who owns it. This one sets out the 2027 Bellinvale flood recovery program of Elderbrook Shire Council, a fictional rural council, in five rows from temporary housing to community wellbeing.
Architecture flow slide a non technical board can follow
An architecture flow slide shows how a request or a record travels through the parts of a system, in order, with a short note on what each part does. This one explains to the board of Brindell Ledger, a fictional bookkeeping app, how a sale recorded in the app becomes a balanced ledger entry.
Want the steps in the builder? Read Add charts, maps and diagrams to slides, then Add, reorder and restructure slides. For everything this generator can do, see the slide maker.