Communication plan, clinical records system upgrade, Rowanmere District Hospital

Communication plan template with audience, message and channel

A communication plan has to make sure each group affected by a change hears the right message, at the right time, from someone they trust, and that their questions come back to the people running it. This four page plan for a hospital clinical records upgrade does that with seven audiences, five key messages, nine channels with owners and a feedback loop with response times.

Create a document with OneCraft4 A4 pages, editable, then download as a PDF

The document, page by page

Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.

Rowanmere District Hospital
2 November 2026

Clinical records upgrade communication plan

Who needs to hear what, when and from whom, before, during and after the go live weekend of 6 and 7 March 2027.

Prepared by
Project communications lead
Date
2 November 2026
Rowanmere District Hospital, clinical records upgrade communication planPage 2 of 4
Rowanmere District Hospital, clinical records upgrade communication planPage 3 of 4
Rowanmere District Hospital, clinical records upgrade communication planPage 4 of 4
1. Purpose

Rowanmere District Hospital will move its clinical records system to a new version over the weekend of Saturday 6 and Sunday 7 March 2027. For about 6 hours on the Saturday night, clinicians will work on paper downtime forms. After go live, screens, order sets and medication charting will look different. 1,400 staff, 220 visiting doctors and the patients in our beds on that weekend all need to know what is happening to them. This plan makes sure each group hears the right message, in time, from someone they trust, and that their questions come back to the project.

2. Audiences
Audience
Size
What changes for them
What they most need
Nurses and midwives
760
New medication charting screens, downtime on night shift
Hands on practice, support on the ward at go live
Medical staff
310
New order sets and results inbox
Short, specific changes; no long sessions
Visiting doctors
220
Remote access login changes
Clear dates and a direct support number
Allied health and pharmacy
140
Referral and dispensing screens
How their workflows connect to the new screens
Administration and clerical
190
Admissions and booking screens
When to stop booking and how to catch up
Patients and families
About 180 inpatients
Brief delays in results during downtime
Reassurance that care continues safely
Executive and board
14
Risk and readiness
A decision point and status at each gate
3. Key messages
1
Why
The current version reaches the end of vendor support in June 2027. The upgrade keeps patient records secure and supported.
2
When
Go live is Saturday 6 March 2027. Downtime runs from 10 pm Saturday to about 4 am Sunday.
3
What it means for you
Each team gets its own list of changed screens; nothing else about your work changes.
4
How you will be ready
A 45 minute practice session for every clinician before 26 February, and super users on every ward at go live.
5
Where to get help
The go live command centre on extension 4400, open 24 hours from 6 to 20 March.
4. Channels, frequency and owners
Channel
Audience
Frequency
Owner
Executive briefing paper
Executive and board
Monthly, then weekly from February
Project sponsor, Director of Nursing
Staff intranet page and FAQ
All staff
Updated weekly
Communications lead
All staff email
All staff
Monthly to February, then weekly
Chief executive
Ward and department huddles
Nurses, allied health
Twice a week from 15 February
Nurse unit managers with a script
Medical staff meeting slot
Medical staff
Monthly grand round, 10 minutes
Chief medical officer
Text message and letter
Visiting doctors
Three times: 8 weeks, 2 weeks and 2 days out
Medical workforce unit
Practice sessions
Clinicians
40 sessions, 25 January to 26 February
Training lead
Bedside card
Patients and families
Handed out on 5 and 6 March
Nurse in charge on each ward
Go live bulletin
All staff
Twice a day, 6 to 12 March
Command centre
Channel
Audience
Frequency
Owner
Executive briefing paper
Executive and board
Monthly, then weekly from February
Project sponsor, Director of Nursing
Staff intranet page and FAQ
All staff
Updated weekly
Communications lead
All staff email
All staff
Monthly to February, then weekly
Chief executive
Ward and department huddles
Nurses, allied health
Twice a week from 15 February
Nurse unit managers with a script
Medical staff meeting slot
Medical staff
Monthly grand round, 10 minutes
Chief medical officer
Text message and letter
Visiting doctors
Three times: 8 weeks, 2 weeks and 2 days out
Medical workforce unit
Practice sessions
Clinicians
40 sessions, 25 January to 26 February
Training lead
Bedside card
Patients and families
Handed out on 5 and 6 March
Nurse in charge on each ward
Go live bulletin
All staff
Twice a day, 6 to 12 March
Command centre
Channel
Audience
Frequency
Owner
Executive briefing paper
Executive and board
Monthly, then weekly from February
Project sponsor, Director of Nursing
Staff intranet page and FAQ
All staff
Updated weekly
Communications lead
All staff email
All staff
Monthly to February, then weekly
Chief executive
Ward and department huddles
Nurses, allied health
Twice a week from 15 February
Nurse unit managers with a script
Medical staff meeting slot
Medical staff
Monthly grand round, 10 minutes
Chief medical officer
Text message and letter
Visiting doctors
Three times: 8 weeks, 2 weeks and 2 days out
Medical workforce unit
Practice sessions
Clinicians
40 sessions, 25 January to 26 February
Training lead
Bedside card
Patients and families
Handed out on 5 and 6 March
Nurse in charge on each ward
Go live bulletin
All staff
Twice a day, 6 to 12 March
Command centre
5. Feedback loop

Messages build in four steps: awareness from November, readiness in January and February, go live from 1 March and settling until 30 April. Communication only works if it travels both ways, so every channel above has a way back in, and every question that reaches the project gets an answer and, where several people ask the same thing, a line on the FAQ.

How staff raise it
What happens next
Response time
Question at a huddle
Unit manager logs it on the shared form
Answered at the next huddle
Intranet question form
Communications lead routes it to the right expert
2 working days
Super user on the ward at go live
Logged with the command centre; urgent issues escalated
Urgent within 1 hour
Survey after go live, 22 March
Results to the executive and every ward
Summary by 9 April

The communications lead reports to the project board every two weeks: messages sent, practice session attendance against the target of 95% of clinicians, the five most common questions, and any group that is not hearing or not listening. A group that falls behind gets a changed approach, not more of the same email.

Section by section

What each section is for, so you can keep the ones you need and drop the rest.

Cover
Spine cover with the hospital, the project and the plan date.
1. Purpose
The go live weekend, the downtime and who is affected.
2. Audiences
Seven audiences with size, what changes and what they need.
3. Key messages
Five numbered messages repeated in every channel.
4. Channels, frequency and owners
Nine channels with audience, frequency and owner.
5. Feedback loop
Four ways questions come back, response times and reporting to the board.

How to adapt this document

First, list your audiences by what changes for them, not by the org chart, and write the one thing each most needs before choosing channels. Second, keep the five message headings but rewrite the content for your change, whether an office move, a merger or a new policy, with the dates and help contacts filled in. Third, give every channel a way for questions to come back and a response time, then report the common questions so the FAQ keeps up.

What makes this document work

Audiences are split by what changes for them

Nurses, doctors, visiting doctors, allied health, clerical staff, patients and the board each get a row with their size, what actually changes for them and what they most need: hands on practice for 760 nurses, a direct support number for 220 visiting doctors, reassurance for about 180 inpatients.

Five messages, said the same way everywhere

Why, when, what it means for you, how you will be ready and where to get help are written once and reused in every channel, with the specifics fixed: downtime from 10 pm Saturday to about 4 am Sunday, and the command centre on extension 4400 from 6 to 20 March.

Every channel has a way back in

The feedback table gives each route a next step and a response time: huddle questions answered at the next huddle, intranet questions in 2 working days, urgent ward issues within 1 hour. The fortnightly report flags any group not hearing the message and changes the approach.

Questions people ask

What is the difference between a communication plan and a stakeholder engagement plan?

A communication plan is mostly about telling people: which messages go to which audiences, through which channels and when. A stakeholder engagement plan is about how much influence each group has on a decision, from being informed to deciding. Projects that change how people work, like this upgrade, often need a communication plan first.

How many key messages should a communication plan have?

Few enough that every channel can repeat them word for word, usually three to five. More than that and different channels drift into different versions of the story. This plan uses five, covering why, when, what it means for you, how you will be ready and where to get help, and repeats them everywhere.

How often should staff hear about a major system change?

Monthly while the change is far away, then weekly in the last month and daily around go live. Frequency should rise as the change gets closer and more concrete. Mix broadcast channels such as email with face to face ones such as team huddles, because people trust a manager's briefing more than an all staff message.

How do you know if a communication plan is working?

Track measures that show understanding and readiness, not just messages sent: attendance at practice sessions against a target, the most common questions, and survey results after go live. If one group keeps asking the same thing or misses sessions, change how you reach them rather than sending more of the same email.

Should patients be told about a hospital system change?

Patients in hospital during a cut over should be told briefly what to expect, such as short delays in results, and reassured that care continues safely. A short card handed out by the nurse in charge, as in this plan, usually works better than a long letter. Patients outside the hospital rarely need to know.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.