Risk register, Terminal 1 refurbishment, September 2026, version 4

Risk register template that works as a monthly meeting document

A risk register is a spreadsheet until someone has to read it out at a meeting, and then it needs a scale, a matrix, owners and a summary of what changed. This one defines its five point scales on page one, rates twelve risks in a table, charts the top five and lists the three that moved since last month.

Create a document with OneCraft4 A4 pages, editable, then download as a PDF

The document, page by page

Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.

Risk register · Terminal 1 refurbishment · version 4
Risk register · Terminal 1 refurbishment · version 4
Risk register · Terminal 1 refurbishment · version 4
Risk register · Terminal 1 refurbishment · version 4
September 2026 review · next review 10 October 2026Page 1 of 4
September 2026 review · next review 10 October 2026Page 2 of 4
September 2026 review · next review 10 October 2026Page 3 of 4
September 2026 review · next review 10 October 2026Page 4 of 4

This register is the live list of risks for the Terminal 1 refurbishment, reviewed at the monthly project meeting. It holds twelve open risks, each rated likelihood times consequence on the five point scales below, with an owner and a response. Three ratings moved since the August review and two risks closed.

Reviewed 12 September 2026
1. How risks are rated
Score
Label
Meaning
1
Rare
Might happen once in the life of the project
2
Unlikely
Not expected, but it has happened on similar projects
3
Possible
Could happen in any given month of the works
4
Likely
Expected to happen more than once during the works
5
Almost certain
Expected to happen this month without action
Score
Label
Cost impact
Time impact
1
Negligible
Under $10,000
Under 1 week
2
Minor
$10,000 to $50,000
1 to 2 weeks
3
Moderate
$50,000 to $150,000
2 to 4 weeks
4
Major
$150,000 to $500,000
1 to 2 months
5
Severe
Over $500,000
Over 2 months

A rating is likelihood times consequence. A risk that is likely and major, 4 by 4, scores 16 and sits in the extreme band, and nothing rated extreme stays untreated past one review.

Likelihood ↓ Consequence →
1
2
3
4
5
5 · Almost certain
5
10
15
20
25
4 · Likely
4
8
12
16
20
3 · Possible
3
6
9
12
15
2 · Unlikely
2
4
6
8
10
1 · Rare
1
2
3
4
5

Rating bands: low 1 to 4, medium 5 to 9, high 10 to 15, extreme 16 to 25.

2. The register
ID
Risk
Cause
Likelihood
Consequence
Rating
Owner
Response
Status
R-01
Roof steel corrosion
Coastal exposure
3
3
9
Structural engineer
Coating program priced into the roofing package
Open
R-02
Glazing delivery slips
Single supplier
3
4
12
Procurement lead
Second supplier qualified, deposit paid on long lead units
Open
R-03
Asbestos in ceiling voids
1988 construction
2
4
8
Site manager
Survey complete, licensed removal under contract, $180,000 allowance
Treated
R-04
Airside access breach
Hoarding gaps
2
5
10
Security manager
Daily hoarding inspection, all trades escorted airside
Open
R-05
Fire system outage at cutover
Staged switchover
2
3
6
Services engineer
Fire watch rostered, temporary detection in live areas
Treated
R-07
Airline schedule change
Seasonal timetable
3
3
9
Airport ops manager
Night works window agreed with the two carriers
Treated
R-08
Tenant noise complaints
Demolition works
4
2
8
Project manager
Noisy works held to the 10pm to 4am window
Monitor
R-09
Dust in baggage belts
Open ceiling voids
3
3
9
Facilities manager
Additional containment over the belts being priced
Open
R-10
Key trade insolvency
Market conditions
2
4
8
Commercial manager
Financial checks quarterly, step in rights in contract
Monitor
R-11
Storms during roof works
Spring weather
3
3
9
Site manager
Temporary roof staged, work stops at named wind triggers
Open
R-12
Contingency exhausted
Asbestos drawdown
2
4
8
Project sponsor
Contingency reviewed monthly against forecast
Monitor
R-14
Escalator parts delay
Obsolete model
3
2
6
Services engineer
Parts ordered early, refurbished spares located
Open
ID
Risk
Cause
Likelihood
Consequence
Rating
Owner
Response
Status
R-01
Roof steel corrosion
Coastal exposure
3
3
9
Structural engineer
Coating program priced into the roofing package
Open
R-02
Glazing delivery slips
Single supplier
3
4
12
Procurement lead
Second supplier qualified, deposit paid on long lead units
Open
R-03
Asbestos in ceiling voids
1988 construction
2
4
8
Site manager
Survey complete, licensed removal under contract, $180,000 allowance
Treated
R-04
Airside access breach
Hoarding gaps
2
5
10
Security manager
Daily hoarding inspection, all trades escorted airside
Open
R-05
Fire system outage at cutover
Staged switchover
2
3
6
Services engineer
Fire watch rostered, temporary detection in live areas
Treated
R-07
Airline schedule change
Seasonal timetable
3
3
9
Airport ops manager
Night works window agreed with the two carriers
Treated
R-08
Tenant noise complaints
Demolition works
4
2
8
Project manager
Noisy works held to the 10pm to 4am window
Monitor
R-09
Dust in baggage belts
Open ceiling voids
3
3
9
Facilities manager
Additional containment over the belts being priced
Open
R-10
Key trade insolvency
Market conditions
2
4
8
Commercial manager
Financial checks quarterly, step in rights in contract
Monitor
R-11
Storms during roof works
Spring weather
3
3
9
Site manager
Temporary roof staged, work stops at named wind triggers
Open
R-12
Contingency exhausted
Asbestos drawdown
2
4
8
Project sponsor
Contingency reviewed monthly against forecast
Monitor
R-14
Escalator parts delay
Obsolete model
3
2
6
Services engineer
Parts ordered early, refurbished spares located
Open
ID
Risk
Cause
Likelihood
Consequence
Rating
Owner
Response
Status
R-01
Roof steel corrosion
Coastal exposure
3
3
9
Structural engineer
Coating program priced into the roofing package
Open
R-02
Glazing delivery slips
Single supplier
3
4
12
Procurement lead
Second supplier qualified, deposit paid on long lead units
Open
R-03
Asbestos in ceiling voids
1988 construction
2
4
8
Site manager
Survey complete, licensed removal under contract, $180,000 allowance
Treated
R-04
Airside access breach
Hoarding gaps
2
5
10
Security manager
Daily hoarding inspection, all trades escorted airside
Open
R-05
Fire system outage at cutover
Staged switchover
2
3
6
Services engineer
Fire watch rostered, temporary detection in live areas
Treated
R-07
Airline schedule change
Seasonal timetable
3
3
9
Airport ops manager
Night works window agreed with the two carriers
Treated
R-08
Tenant noise complaints
Demolition works
4
2
8
Project manager
Noisy works held to the 10pm to 4am window
Monitor
R-09
Dust in baggage belts
Open ceiling voids
3
3
9
Facilities manager
Additional containment over the belts being priced
Open
R-10
Key trade insolvency
Market conditions
2
4
8
Commercial manager
Financial checks quarterly, step in rights in contract
Monitor
R-11
Storms during roof works
Spring weather
3
3
9
Site manager
Temporary roof staged, work stops at named wind triggers
Open
R-12
Contingency exhausted
Asbestos drawdown
2
4
8
Project sponsor
Contingency reviewed monthly against forecast
Monitor
R-14
Escalator parts delay
Obsolete model
3
2
6
Services engineer
Parts ordered early, refurbished spares located
Open
3. Top risks this month
Five highest current ratings by risk ID
036912Rating, likelihood x consequenceR-02 Glazing deliveryR-04 Airside accessR-01 Roof corrosionR-09 Baggage belt dustR-11 Roof work storms
4. Movement since last review
ID
Was
Now
Why
R-03
16
8
Removal contract in place and air monitoring clear for three weeks
R-05
12
6
Temporary detection commissioned in all live areas
R-09
6
9
Two belt faults traced to dust; containment now being priced
5. Closed this month
ID
Risk
Why closed
R-06
Temporary power capacity
Permanent supply energised 2 September
R-13
Crane permit delay
Permit issued 4 September, lifts completed
6. Actions due before the next review
Action
Owner
Due
Price and approve baggage belt containment
Facilities manager
26 September
Place the backup glazing order or release the deposit
Procurement lead
30 September
Table the contingency forecast after asbestos drawdown
Project sponsor
10 October
Review

Reviewed at the September project meeting. Version 5 is due at the next review on 10 October 2026.

Elena Voss, Project Manager
Name
:
Date
:
Richard Amaya, Project Sponsor
Name
:
Date
:

Section by section

What each section is for, so you can keep the ones you need and drop the rest.

Review stamp
Reviewed 12 September 2026, stamped under the version 4 header.
Likelihood scale
Scores 1 to 5, each with a plain sentence meaning.
Consequence scale
Scores 1 to 5 with dollar and time thresholds.
The 5 by 5 matrix
Ratings coloured by band, low 1 to 4 up to extreme 16 to 25.
The register
Twelve risks with cause, rating, owner, response and status.
Top risks this month
A bar chart of the five highest current ratings by ID.
Movement since last review
Three rows of was, now and why, including R-03 falling 16 to 8.
Closed this month
Two risks retired, each with the reason.
Actions due
Three actions with owners and dates before the 10 October review.
Review sign off
Project manager and sponsor sign, next review dated.

Likelihood, consequence and the matrix: making two people rate the same way

Every rating argument traces back to undefined scales. Fix it by writing a plain sentence for each likelihood score, this register uses "could happen in any given month of the works" for a 3, and hard thresholds for each consequence score, dollars and weeks, not adjectives. The matrix does the rest: likelihood down the side, consequence across the top, the product in each cell, coloured by band. The bands are policy, not decoration. Low means accept and watch; medium means an owner and a response; high is reported monthly; extreme, 16 and up, does not survive a review untreated. Write the bands next to the matrix so the rule travels with the number.

How to adapt this document

For an operational register covering a whole business rather than a project, swap the project sections for category groupings, financial, people, systems, compliance, and review quarterly instead of monthly; the scales and matrix stay. For a WHS register, keep the same 5 by 5 but write the consequence scale in injury terms rather than dollars, and link each row to the safe work method statement for the activity that creates it. For a small project, a 3 by 3 matrix with three bands is honest and quicker to rate; keep the movement section even then, because what changed since last time is the part every audience actually reads.

What makes this document work

The scales carry dollar and time thresholds

Consequence 4 means $150,000 to $500,000 or one to two months, in a table on page one. Without thresholds, one manager's 4 is another's 2 and the matrix is theatre; with them, two people rating the same risk land on the same square, which is the whole point of having a scale.

R-03 shows a rating falling from 16 to 8

The asbestos risk entered the register at extreme, 16, and sits at 8 after a survey, a licensed removal contract and a $180,000 allowance. The movement table records the fall and why. A register that can show a number dropping because of work done is the register that proves the process is worth the meeting.

The movement table means the meeting reads three rows

Twelve risks are too many to talk through monthly. Section four lists only what changed, three risks with was, now and a one line why, and section five lists the two that closed. The meeting covers those five rows plus the top five chart; the other pages exist for whoever wants the detail.

Questions people ask

What is a risk register?

A living list of the risks to a project or operation, each with a rating on a defined scale, an owner and a response, reviewed on a cycle. This example is version 4 of a monthly register: twelve open risks, three ratings moved, two closed, the next review dated in the footer.

How do you rate a risk?

Likelihood times consequence, each scored one to five on scales the document itself defines. A possible risk with major consequence scores 3 by 4, 12, high band. The rating is only as good as the scale definitions, which is why this register spends its first page on them.

How many risks should a register have?

As many as genuinely have an owner and a response, twelve here. A register padded to fifty rows to look thorough is unreadable at a meeting and unmaintained by month three. If a risk is not worth assigning to a named person, it is not worth a row.

Who owns a risk?

The person who can actually act on the response, not the most senior person in the room. Here the asbestos risk belongs to the site manager running the removal contract, the insolvency risk to the commercial manager running the financial checks. The sponsor owns exactly one: contingency running out.

What is the difference between a risk register and a risk assessment?

The assessment is the analysis of one activity at one time; the register is the list of all live risks over time, with versions and reviews. For workplace health and safety, the activity level document is the safe work method statement, and the WHS risks land in the register with the same scales.

How often should a risk register be reviewed?

Monthly for a live project, quarterly for operations. This one is stamped with its review date, carries version 4 in the running header, and lists the actions due before version 5 on 10 October, so the cycle is visible in the document itself.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.

Make my risk register template that works as a monthly meeting document

Other document examples

Want the steps in the builder? Read Create a document with AI, then Document layout, spacing and page breaks. For everything this generator can do, see the document maker.

Sources