Kingsway Street office fit out: Monthly status report, August 2026

Project status report template with a RAG status

Month four of the Kingsway Street office fit out. The report opens Amber, nine days behind and 61 per cent complete, with a forecast cost of $2.41M against a $2.35M budget, and the first sentence names the cause: asbestos sheeting found behind walls during demolition. Five pages carry progress by work package, a budget table, a spend chart, five risks and three decisions the sponsor has to make.

Create a document with OneCraft5 A4 pages, editable, then download as a PDF

The document, page by page

Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.

Project status report

Kingsway Street office fit out: Monthly status report, August 2026

Kingsway Street office fit out

Project Manager
For the period ending 31 August 2026
Kingsway Street office fit out · Monthly status report · August 2026Page 2 of 5
Kingsway Street office fit out · Monthly status report · August 2026Page 3 of 5
Kingsway Street office fit out · Monthly status report · August 2026Page 4 of 5
Kingsway Street office fit out · Monthly status report · August 2026Page 5 of 5
Amber
Overall status
9 days behind
Schedule
61% complete
Progress
$2.41M
Forecast cost
Executive summary

The project is tracking at an Amber status due to a nine-day delay to the critical path. This was caused by the discovery of hazardous materials (asbestos-containing sheeting) behind existing walls during demolition, which required specialist removal and environmental clearance before framing could proceed. While this has impacted the schedule, a recovery plan is in development. The budget is under pressure, with a forecast cost at completion of $2.41M against the $2.35M budget, primarily due to the costs of remediation and potential acceleration measures. All other work packages are progressing as planned.

Progress this period
1
WP01: Demolition & Strip-out
Completed, including removal of all redundant partitions, ceilings, and services. Hazardous material removal complete.
2
WP02: Structural Works
All required structural steel for new openings installed and certified.
3
WP03: Framing & Partitions
90% complete. All internal walls framed, awaiting final sections pending services rough-in.
4
WP04: First Fix Services (Elec/Mech/Hyd)
75% complete. In-wall electrical cabling, hydraulic pipework, and HVAC ducting runs are substantially complete.
5
WP05: Plastering & Ceilings
Commenced. First pass of plasterboard hanging is underway in completed framing zones.
6
WP07: Glazing
Internal glazed partition frames delivered to site and installation commenced.
Budget summary
Work package
Budget
Committed
Spent to date
Forecast
Preliminaries & Management
$350,000
$350,000
$210,000
$350,000
Demolition & Hazmat
$120,000
$165,000
$165,000
$165,000
Partitions & Ceilings
$480,000
$480,000
$290,000
$480,000
Services (Elec/Mech/Hyd/Fire)
$750,000
$750,000
$450,000
$765,000
Finishes (Flooring/Paint/Joinery)
$500,000
$450,000
$50,000
$500,000
Contingency
$150,000
$0
$0
$150,000
Total
$2,410,000
Spend profile
  • Actual Spend
  • Planned Spend
May 26Jun 26Jul 26Aug 260400K800K1.2M1.6MCumulative Spend ($AUD)
Key risks and issues
Risk / Issue
Likelihood
Impact
Owner
Mitigation / Action
Schedule delay due to latent conditions (Issue)
N/A
High
PM
Develop schedule recovery options (weekend work, re-sequencing) for Steering Committee approval.
Further latent conditions discovered
Low
High
PM
Intrusive investigation completed in representative areas. Allowance held in contingency.
Long-lead item delay (Joinery)
Medium
Medium
Contractor
Shop drawings approved. Weekly progress checks with manufacturer established.
Key trade availability for acceleration
Medium
High
Contractor
Early engagement with key trades (joiners, floor layers) to forecast resource requirements for potential overtime.
Stakeholder approval delays on finishes
Medium
Medium
Client Rep
Decisions required table issued monthly. Clear deadlines communicated for all selections.
Decisions required
1
Approval for schedule recovery strategy
A decision is required on the preferred acceleration strategy (e.g. weekend work) to recover the 9-day delay. Consequence: Without approval, the project completion date will be extended, impacting business readiness and move-in plans.
2
Approval of Variation #03: Hazardous Material Removal ($45,000)
Formal approval is required for the costs associated with the asbestos removal. Consequence: Non-approval will result in a payment dispute with the contractor and impact project contingency reporting.
3
Final selection of breakout area furniture
The final furniture selection is required to meet supplier lead times. Consequence: A delay in decision will require re-selection from available stock, compromising the design intent, or cause further delays to project completion.
Plan for next period (September 2026)
Week 1
Complete framing and plastering
Week 2
Complete services rough-in and close walls/ceilings
Week 3
Commence flooring preparation and painting
Week 4
Commence cabinet and joinery installation

Section by section

What each section is for, so you can keep the ones you need and drop the rest.

Status at a glance
Four tiles: overall status, days behind, percentage complete and forecast cost.
Executive summary
The cause of the delay, the recovery plan under way and the budget pressure in one paragraph.
Progress this period
Six work packages with a percentage or a completion note each, from demolition to glazing.
Budget summary
Budget, committed, spent to date and forecast for six packages including contingency, with the total forecast.
Spend profile
Cumulative actual against planned spend from May to August.
Key risks and issues
Five entries with likelihood, impact, owner and mitigation, including the open schedule issue.
Decisions required
Three numbered decisions with a stated consequence for each if it is not made.
Plan for next period
Four weeks of September with one milestone each.

Who this is for

A project manager reporting up to a sponsor or a steering group on a project big enough to have a budget line and small enough that one person still knows all of it. A fit out, a system migration, an office move. If the project has a programme office with its own template, use theirs; the value of this one is that it is short enough to actually write every month.

How to adapt this document

For a weekly one pager, keep the status line, the progress block and the decisions needed, and drop the budget table to a single forecast number. Budgets do not move enough week to week to earn a table. For a longer programme, add a second page with one row per workstream, each carrying its own colour, so the top level status is visibly the sum of something rather than a judgement call. Whatever you change, change it once and keep it, because a template that shifts shape every month forces the reader to re-learn it and they will stop.

What makes this document work

Status is one word and a reason

Amber, nine days behind and asbestos named in the first sentence of the summary. No sponsor should read three pages to learn that.

Budget shows the forecast

Six work packages with budget, committed, spent and forecast side by side, so the $45,000 hazmat overrun and the $15,000 services pressure are visible before they are invoiced.

It asks for decisions

Three numbered decisions, each with a consequence attached: the recovery strategy, variation 3 for the asbestos removal, and the furniture selection that has a lead time.

Questions people ask

What goes in a project status report?

Six blocks, in the same order every month: the status colour, progress against plan, budget against forecast, risks, the decisions you need from the reader, and what happens next. This example runs exactly that shape. Keeping the shape fixed is most of the value, because a reader learns where to look and stops reading the parts that have not moved.

How often should you report?

Monthly for most projects, weekly through a critical phase such as a go live or a migration cutover. Consistency matters more than frequency: a report that always lands on the first Tuesday gets read, and one that appears when there is news gets read as bad news before anyone opens it.

Should bad news go in the report?

Yes, at the top, in the status line. This example opens Amber and nine days behind, so nobody has to hunt for it. A report that buries a delay in the risk table stops being useful the moment the delay surfaces, and the next one gets read with suspicion. Put the number in the first sentence and the recovery plan in the next.

How many pages does a status report need?

Five is plenty. This one fits status, progress, budget, risks and decisions into five and keeps the same shape every month.

What does Amber actually mean?

That the project can still hit its dates or budget, but only if something is decided or changed now. Green means on track with no help needed, red means the plan as written no longer works. The colours only mean anything if you define them once and hold to it, so print the definition in the report the first few months.

Should the risks be on page one?

The two or three that could move the status colour, yes. The full register belongs at the back or in its own document. A page one risk table with fourteen rows scored low tells a reader nothing, and it trains them to skip the section that matters most when a real risk finally appears in it.

Who is the report actually for?

The person who can unblock you, which is usually a sponsor or a steering group rather than the team. That is why this example has a decisions needed section: it is the only part where the reader has a job. Write everything else to be skimmed and that section to be answered.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.

Make one like this

Other document examples

Want the steps in the builder? Read Create a document with AI, then Style text and add callouts, stats and lists. For everything this generator can do, see the document maker.

Sources

Written and checked by the OneCraft team. Last checked .