Purchase order PO-8842

Purchase order

A civil contractor buys structural steel for a job that starts in three weeks. The order is written by the buyer, not the seller, and almost everything on it exists to stop a surprise arriving on the truck.

Create a document with OneCraft3 A4 pages, editable, then download as a PDF

The document, page by page

Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.

Glenrowan Civil Contractors
ABN 72 338 907 145 · 18 Quarry Road, Riverstone NSW 2765 · purchasing@glenrowancivil.example · 02 9627 3300
Glenrowan Civil Contractors
Glenrowan Civil Contractors
Purchase order PO-8842
19 Aug 2026
Raised
9 Sep 2026
Required on site
30 days EOM
Terms
$38,209.60
Order total
Supplier
Tanner Steel Supplies Pty Ltd 6 Foundry Way Wetherill Park NSW 2164 ABN 41 220 668 913
Deliver to
Lot 14, Bandon Road Riverstone NSW 2765 Marco Della, 0412 887 019 Gate 2, western hardstand
Invoice to
Glenrowan Civil Contractors Accounts Payable 18 Quarry Road Riverstone NSW 2765
Items ordered
Part
Description
Qty
Unit
Amount
UB310-46
Universal beam 310UB46.2, 9.0m, grade 300
12
$1,284.00
$15,408.00
PFC250
Parallel flange channel 250PFC, 6.0m
8
$742.00
$5,936.00
SHS100-5
SHS 100 x 100 x 5.0, 8.0m lengths
20
$386.00
$7,720.00
PL12-BP
Base plate 300 x 300 x 12, drilled
24
$96.00
$2,304.00
BOLT-M20
M20 x 75 galvanised bolt sets, box of 25
16
$118.00
$1,888.00
Goods subtotal
$33,256.00
Delivery, two loads to site
$1,480.00
Subtotal before GST
$34,736.00
GST 10 percent
$3,473.60
Order total
$38,209.60
Delivery
Window
Two loads, 9 and 10 September 2026, between 7am and 11am. Ring the site contact the afternoon before with a truck number.
Access and unloading
Gate 2 only. Supplier unloads with its own truck mounted crane. No forklift is available on site.
Paperwork on arrival
Delivery docket quoting PO-8842, and the mill test certificates for the beam, channel and SHS. A load without certificates is turned around.
Terms of purchase
1
Acceptance
This order is an offer to buy. It is accepted when the supplier acknowledges it or despatches any part of it, whichever happens first. Terms printed on a supplier acknowledgement, docket or invoice do not form part of this contract.
2
Price
The prices above are firm until 30 September 2026 and are not subject to rise and fall. Any surcharge, levy or fuel adjustment not shown on this order will not be paid.
3
Variations
Nothing outside this order is to be supplied without a written variation signed by the site manager. A verbal instruction from anyone on site, including a foreman, is not authority to supply or to charge.
4
Inspection and rejection
Goods are inspected within five business days of delivery. Anything damaged, short, or not to the specification above is rejected in writing, and the supplier collects it at its own cost within ten business days.
5
Documentation
Test certificates to AS/NZS 3679.1 are required for all hot rolled sections supplied on this order. Payment for a delivery is not due until its certificates have been received, regardless of the invoice date.
6
Invoicing and payment
Invoice each delivery separately, quoting PO-8842 and the delivery docket number. Terms are 30 days from the end of the month of a correct invoice. Title passes on delivery and risk passes when the load is unloaded and accepted.
Invoices without this order number are returned
Our accounts system matches every invoice to an order line before it is scheduled for payment. An invoice that does not quote PO-8842 cannot be matched and is sent back the same day, which usually costs a month.
Returning this order

Sign the acknowledgement below and email it to purchasing@glenrowancivil.example within two business days. Signing confirms the parts, the prices and both delivery dates. If either date cannot be met, say so on the acknowledgement rather than after the load is booked, because the crane and the crew are hired against these dates.

Raised by
Kate Ferreira, purchasing officer
Cost code
14-STRUCT-02, Bandon Road stage 2
Authorised for Glenrowan Civil Contractors
Name
:
Position
:
Date
:
Order acknowledged for Tanner Steel Supplies
Name
:
Position
:
Date
:

Section by section

What each section is for, so you can keep the ones you need and drop the rest.

Contractor letterhead
Buyer name, ABN, purchasing email and phone on every page, since the supplier will copy the order into its own system.
Raised, required on site, terms, total
The order date, the date the steel has to be standing on the slab, the payment terms and the committed value.
Supplier, deliver to, invoice to
Three separate addresses, because the goods, the paperwork and the payment all go to different places.
Items ordered
Five lines with part numbers, full section descriptions, quantities and unit prices, in the wording the supplier catalogue uses.
Delivery and GST totals
Goods subtotal, the freight for two loads priced separately, then GST and the committed order total.
Delivery window
The two dated loads, the hours, the notice call and the truck number the site expects the afternoon before.
Access and unloading
Which gate, and the fact that the supplier unloads with its own crane because there is no forklift on site.
Paperwork on arrival
Delivery docket quoting the order, plus mill certificates, with a plain statement that a load without them is turned around.
Terms of purchase
Six numbered clauses on acceptance, firm pricing, written variations, inspection and rejection, documentation, and invoicing.
Unmatched invoice warning
Explains the three way match and what happens to an invoice that cannot be tied to an order line.
Acknowledgement blocks
One signature for the buyer authorising the spend, one for the supplier confirming the parts, prices and both dates.

Clauses in this document

What makes this document work

The buyer sets the terms

Clause one says that anything printed on the supplier acknowledgement, docket or invoice does not form part of the contract. That sentence is the reason to raise an order rather than simply accept a quote.

Payment is tied to the paperwork

Mill test certificates are named as a condition, and payment for a load is not due until they arrive whatever the invoice date says. Steel without certificates is steel nobody can sign off.

It tells the truck exactly what to do

Two dated loads, a four hour window, one gate, unloading by the supplier's own crane because the site has no forklift, and a mobile number to ring the afternoon before.

Questions people ask

What is a purchase order?

A written offer from a buyer to a seller, listing exactly what is being bought, at what price, delivered when and where. It becomes a contract when the supplier acknowledges it or ships against it.

What is the difference between a purchase order and an invoice?

The order comes first and is written by the buyer. The invoice comes after delivery and is written by the seller. Accounts payable matches one to the other before anything is scheduled for payment.

Why do invoices get returned for a missing order number?

Because a three way match of order, delivery docket and invoice is what stops duplicate and phantom billing. An invoice with no order number cannot enter that process, so it goes back rather than into a queue.

Can a purchase order include the buyer's own conditions?

Yes, and that is most of its value. This one fixes prices to a date, refuses unnamed surcharges, rules out verbal variations, sets an inspection window and states when title and risk pass.

Why does the order set out access and unloading?

Because a construction site is not a loading dock. This order names the access route, the unloading arrangement and the delivery window in their own sections. A truck that arrives without a forklift booked, or outside the window, costs the supplier a return trip and the contractor a day of the program.

What paperwork has to arrive with the delivery?

The order lists it, so the driver is not turned away. On this one that means the delivery docket quoting the order number and the test certificates for the materials. Naming them on the purchase order puts the requirement in front of the supplier at the point they are picking the load.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.

Make one like this

Other document examples

Want the steps in the builder? Read Create a document with AI, then Every document component and when to use it. For everything this generator can do, see the document maker.

Sources

Written and checked by the OneCraft team. Last checked .