Payment schedule, Tidewater Dental fit out

Payment schedule

A $184,800 fit out is paid in six milestones, and every one of them is a piece of work rather than a date. The running balance column is the part both sides check, because it falls to zero only when the handover pack changes hands.

Create a document with OneCraft5 A4 pages, editable, then download as a PDF

The document, page by page

Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.

Payment schedule

Tidewater Dental, Suite 4 fit out

Schedule 2 to the building contract between Halcyon Interiors Pty Ltd and Tidewater Dental Pty Ltd

Halcyon Interiors Pty Ltd
Contract dated 24 August 2026
Schedule 2, payment schedule · Halcyon Interiors Pty Ltd · ABN 73 508 116 249Page 2 of 5
Schedule 2, payment schedule · Halcyon Interiors Pty Ltd · ABN 73 508 116 249Page 3 of 5
Schedule 2, payment schedule · Halcyon Interiors Pty Ltd · ABN 73 508 116 249Page 4 of 5
Schedule 2, payment schedule · Halcyon Interiors Pty Ltd · ABN 73 508 116 249Page 5 of 5
Payment schedule
$184,800
Contract sum
6
Milestones
7 days
Payment terms
2 Dec 2026
Handover

This schedule sets when money moves on the Suite 4 fit out. Every figure includes GST. Nothing is payable on a date alone. A milestone falls due when the work it names is finished and the evidence listed against it has been supplied, and the date in the last column is the target for that to happen.

The schedule
Milestone
Share
Amount
Target date
Balance after
1. Deposit on signing
10%
$18,480
1 Sep 2026
$166,320
2. Design sign off and shop drawings issued
15%
$27,720
16 Sep 2026
$138,600
3. Materials ordered and delivered to site
20%
$36,960
7 Oct 2026
$101,640
4. Rough in complete, electrical, hydraulic and framing
20%
$36,960
28 Oct 2026
$64,680
5. Joinery installed and painting complete
20%
$36,960
18 Nov 2026
$27,720
6. Practical completion and handover
15%
$27,720
2 Dec 2026
$0
Total
100%
$184,800
What releases each payment
1
Signed contract and site access
The deposit is claimable once both parties have signed and the owner has given written access to the suite. Nothing is ordered and no trade is booked before it clears.
2
Client approval on the drawing set
Claim 2 needs the signed shop drawing register, every sheet initialled, and the joinery finish schedule confirmed. This is the last point at which a layout change costs nothing.
3
Supplier invoices and a delivery docket
Claim 3 is the money that leaves the builder first. It needs the supplier invoices for cabinetry, tiles and the sterilisation bench, plus a delivery docket signed on site.
4
Rough in inspection certificates
Claim 4 needs the electrical certificate of compliance and the plumbing inspection, both dated, plus photographs of the framing before it is closed up.
5
Photographs and a trade sign off
Claim 5 needs dated photographs of every room and a written sign off from the joiner and the painter that their scope is complete and free of defects.
6
Practical completion certificate and the handover pack
Claim 6 needs the certificate signed by both parties, the defects list agreed and dated, warranties, operating manuals and the keys. It is the only claim the owner can withhold against an open defect.
GST
Line
Amount
Contract sum excluding GST
$168,000.00
GST at 10%
$16,800.00
Contract sum including GST
$184,800.00

GST is one eleventh of every amount in the schedule, so a claim of $36,960 carries $3,360 of GST. Each claim is issued as a tax invoice on the day the milestone is certified, and the owner claims the credit in the period the invoice is dated.

Variations
Nothing changes without a variation order
A variation is priced in writing, signed by both parties and numbered before the work starts. Verbal instructions on site are recorded but are not authority to proceed and are not payable.
Where the money lands
An approved variation is added to the next milestone that has not yet been claimed, not spread across the remainder. The running balance in the table is reissued with the variation order so both parties are reading the same number.
Instead of retention
No retention is held on any claim, so every line in the table is the full amount. The protection sits in the final milestone instead. Fifteen per cent of the contract sum, $27,720, is not claimable until practical completion is certified and the agreed defects list is closed, which is the largest single payment left on the job.
When a payment is late
Terms
Seven days from the date of a valid claim, by electronic transfer to the account named on the invoice
Interest
Ten per cent a year, calculated daily on the unpaid amount, running from the eighth day
Suspension
After fourteen days unpaid, on five business days written notice, and the program moves out by the days lost
Disputed amounts
The undisputed part is paid on time and the disputed part is stated in writing within five business days
Slipped dates
A milestone reached early may be claimed early. One delayed by the owner needs a written program revision
Claiming a milestone
1
The builder emails a claim with the evidence attached
One email, one milestone, the evidence named above, and a tax invoice for the exact amount.
2
The owner certifies or objects within three business days
Certification is a reply saying the milestone is reached. An objection names the part that is not finished. Silence past three business days counts as certification.
3
Payment follows seven days from the valid claim
Not from certification, and not from month end. The clock runs from the day the claim was sent.
Who may certify
Dr Priyanka Raghavan or Dr Simon Teale for the owner, either one alone
Where claims are sent
accounts@tidewaterdental.example, copied to the practice manager

This schedule is version 1 and forms part of the building contract dated 24 August 2026, which governs where the two disagree. Schedule 1 scope of works and Schedule 3 finishes are read with it.

Signed for Halcyon Interiors Pty Ltd
Name
:
Position
:
Date
:
Signed for Tidewater Dental Pty Ltd
Name
:
Position
:
Date
:

Section by section

What each section is for, so you can keep the ones you need and drop the rest.

Cover
The job, both parties and the contract this schedule attaches to, so the document is never read on its own.
Headline terms
Contract sum, milestone count, payment terms and the handover date.
The schedule
Six milestones with the share, amount, target date and the balance remaining after each, ending at zero.
What releases each payment
Six numbered notes naming the certificate, photograph or sign off that makes a claim valid.
GST
The contract sum split into the amount excluding GST, the tax and the total, with the one eleventh rule stated.
Variations
Why nothing changes without a signed variation order, and which milestone an approved variation lands in.
Instead of retention
The reason no retention is held and where the equivalent protection sits.
When a payment is late
Terms, interest, the suspension right, how a disputed amount is handled and what happens when dates slip.
Claiming a milestone
Three numbered steps covering the claim email, the three day certification window and when the seven days starts.
Who may certify
The named people who can certify for the owner and where claims are sent.
Execution
The statement that the contract governs a conflict, and signature blocks for both parties.

Clauses in this document

What makes this document work

The balance column reconciles to zero

Ten, fifteen, twenty, twenty, twenty and fifteen per cent add to one hundred, and the six amounts add to $184,800. Each row shows what is left after it, ending at nil, so neither party has to keep a separate running total.

Every milestone names its evidence

A certificate of compliance, a signed drawing register, dated photographs, a delivery docket. A claim without the named document is not a valid claim, which is stated once and then applied six times.

Retention is replaced by something visible

Rather than holding five per cent of every claim, the schedule makes the final fifteen per cent, $27,720, conditional on practical completion and a closed defects list. The protection is the same size and much easier to argue about.

Questions people ask

What is a payment schedule?

A table setting out when money is payable under a contract, what triggers each payment, and how much is left afterwards. On a construction job it is usually milestone based rather than monthly, so payment follows work rather than the calendar.

Should milestone dates be binding?

The dates here are targets, and the trigger is the work. A milestone reached early can be claimed early, and one delayed by the owner does not move the later dates without a written program revision. That keeps the schedule honest in both directions.

How is GST handled on progress claims?

Every amount in the table includes GST, which is one eleventh of it, so a $36,960 claim carries $3,360 of tax. Each claim is issued as a tax invoice on the day the milestone is certified, and the owner claims the credit in that period.

What happens if a payment is late?

Interest runs at ten per cent a year from the eighth day, and after fourteen days unpaid the builder may suspend on five business days written notice, with the program moving out by the days lost. Disputed amounts have their own five day rule.

What does the schedule use instead of retention?

A defects holdback structured differently, set out in its own section. Retention ties up money for months and is a common source of dispute on small fit outs. Naming the alternative in the schedule, rather than leaving it to the head contract, means both parties priced the same arrangement.

Who is allowed to certify a milestone?

Only the person named in the schedule. This document has a section for it, because a milestone claim signed off by whoever was on site that day is how progress payments go wrong. Naming the certifier at the start gives the contractor one person to chase and the client one point of control.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.

Make one like this

Other document examples

Want the steps in the builder? Read Create a document with AI, then Every document component and when to use it. For everything this generator can do, see the document maker.

Sources

Written and checked by the OneCraft team. Last checked .