What is a SWMS?

A safe work method statement is the document prepared before high risk construction work starts. It names the work, identifies the hazards, describes the control measures and how they will be put in place, monitored and reviewed. Under the model work health and safety regulations it is required for the listed categories of high risk construction work.

A SWMS is one of very few workplace documents whose absence is itself an offence, which is why they get produced even where they are not read. A statement written for a regulator rather than for a crew protects nobody.

· Co-founder

5 min read · Published

SWMS, JSA and a risk assessment
SWMSJob safety analysisRisk assessment
Required by lawYes, for high risk construction workNo, it is a good practice toolSometimes, depending on the hazard
CoversOne activity of high risk construction workAny task, broken into stepsA hazard or a workplace
Written byThe person conducting the business doing the work, with the workersThe crew doing the taskWhoever manages the hazard
HeldAt the workplace while the work is doneWith the crewIn the safety management system
ReviewedWhen the work changes or a control failsBefore each jobPeriodically and after an incident
Read byThe workers, the principal contractor, the regulatorThe crewManagers and health and safety representatives

When a SWMS is actually required

The trigger is high risk construction work, which the model regulations define as a list of specific activities rather than as a general standard of danger. Work involving a risk of a person falling more than two metres, work on or near energised electrical installations, work in or near a confined space, demolition, asbestos, tilt up and precast concrete, work on or near pressurised gas mains, work in an area with movement of powered mobile plant, and several others are on the list. Each state and territory administers its own version, so the list and the detail should be checked against the regulator where the work is happening. The practical consequence is that the question is not how risky does this feel, but does this activity appear on the list, and that is a question with a checkable answer.

What makes a SWMS useful rather than filed

A statement that matters is written for the people doing the work, in the order they will do it. Each step of the activity, the hazards that step creates, the controls applied, and who is responsible for putting each control in place. Controls should be specific enough to check on site: an anchor point rated and installed at a named location beats working at heights procedures followed. The hierarchy of controls belongs in the thinking rather than in the document as a heading, so if a hazard is controlled only by personal protective equipment, the statement should say why elimination, substitution and engineering controls were not used. That question, answered honestly, is where most of the safety value in the exercise actually sits.

Consultation is part of the obligation

A SWMS prepared in an office and handed to a crew has missed a requirement rather than just an opportunity. The workers doing the task have to be consulted in developing it, and they are usually the only people who know which control will be quietly abandoned by ten in the morning because it makes the job impossible. Sign on by the crew records that they were briefed on the statement, which is different from having written it. Where subcontractors are involved, the principal contractor generally has to be given a copy before the work starts, and the statement has to be available at the workplace while the work is being done and kept for a defined period after.

Why generic statements fail

The commonest failure is a template downloaded and reused across sites with the site name changed, which produces a document that describes hazards that are not present and misses the ones that are. A close second is a SWMS covering an entire project rather than one activity, so the controls are too general to apply to anything. A third is a statement that is never reviewed when conditions change, when the weather turns, the sequence shifts or a control turns out not to work. Review is not an annual event here; it is triggered by the work changing. A fourth is length: a forty page statement will not be read at a toolbox talk, and a document nobody reads provides no defence to anybody.

Building a SWMS as a document

A SWMS is a structured tabular document, usually three to eight pages, with the activity breakdown as the central table: step, hazard, risk rating, control, responsible person. Tables are one of the forty five component types and a five column table prints well in portrait. Callouts have four variants, which covers marking a stop work trigger and a high risk step without inventing a colour code. One signature block party is one signer, so a statement signed by the supervisor and each crew member needs a party per person. At this length the document can carry a contents list, and contents are only used on long documents with headings that match exactly.

Questions people ask

Who is responsible for preparing the SWMS?

The business carrying out the high risk construction work prepares it, in consultation with the workers who will do the job. A principal contractor does not write a subcontractor's statement for them, though they can set requirements, ask to see it before work starts and stop work that is not being done in accordance with it.

How long must a SWMS be kept?

Keep it available at the workplace while the work is being carried out, and retain it afterwards for the period the regulations in that jurisdiction require. If a notifiable incident occurs in connection with the work, the statement must be kept for longer, because it becomes part of the record an inspector will ask for.

Can one SWMS cover several jobs?

Only where the work is genuinely the same activity with the same hazards and the same controls. Repeating an identical installation across twenty houses can reasonably share a statement with site specific details attached. A statement that covers a whole build, or several trades, will be too general to control anything and is likely to be treated as inadequate.

What happens if there is no SWMS?

Carrying out high risk construction work without one is a breach in its own right, separate from any injury, and regulators do issue notices and penalties for it. Work can also be stopped by a principal contractor or an inspector. The document is cheap by comparison, which is why the absence is usually a process failure rather than a decision.

Is a SWMS the same as a safe operating procedure?

No. A safe operating procedure covers a machine or a task and is usually a standing document, often displayed near the equipment. A SWMS covers a particular high risk activity at a particular workplace and is prepared for that work. They complement each other, and a SWMS can refer to a procedure rather than repeating it.

Does a SWMS need to be signed?

The regulations focus on preparation, consultation and availability rather than signatures, but recording that each worker was briefed on it is standard practice and is what most principal contractors require. A sign on sheet attached to the statement, with the date and the name of the person who delivered the briefing, is the usual form.

Make one with documents

The button opens the generator with this use case already described. Change the wording to match your own.

Create a document with OneCraft