Orrell Facilities Onboarding Kickoff

Customer onboarding deck

Eleven slides from Tesselate, an invented field service product, to Orrell Facilities Group, an invented customer with 240 engineers across six regions. This is the meeting where an account changes hands, so it repeats the sales conversation back before anything else, writes down the four numbers the account will be judged on with their August baselines, and spends a slide on the five things only the customer can do.

Create a presentation with OneCraft11 slides, read in order

Every slide, in order

The whole deck as it renders, one slide after another. Read it the way the audience would.

TESSELATE

KICKOFF

28 SEP 2026

GO LIVE

12 JAN 2027

A tall editorial photograph of a field service van parked outside a large commercial building at dawn, rear doors open showing neatly racked tools and parts bins, wet tarmac, cold blue morning light, documentary style, no people, no readable text, no logos

ONBOARDING PLAN

The First

Ninety Days

At Orrell

WORDS BY NAOMI ADEYEMI

CUSTOMER SUCCESS LEAD · TESSELATE · 28 SEPTEMBER 2026

Slide 1 · cover · Names the meeting, the date and the go live, so nobody in the room is unclear what is being started.

Ninety Minutes

Four parts. Only the third one needs a decision from you today.

01
Your team

Who you will actually be dealing with for the next two years, and how to reach each of them.

02
Success criteria

The four numbers this account gets judged on, with the baselines we measured in August.

03
Scope and plan

What is in, what is out, and the ninety day plan. This is the part we need you to agree today.

04
What we need

Five things only Orrell can do, with an owner and a date against each one.

02

Slide 2 · agenda · Shapes a ninety minute kickoff into four parts and says which one is the decision.

Who You Deal With Now That The Sale Is Done

Naomi Adeyemi

Customer success lead, and the person accountable for the four success criteria. Weekly during the first ninety days, monthly after that. Escalate to her before anyone else.

Dev Sarangi

Implementation engineer. On site at Warrington for the first three weeks, then two days a fortnight until go live. He owns the data migration and the integration to your finance system.

Priya Naidoo

Trainer. Runs the twenty engineer sessions and the two supervisor sessions. She writes the job aids, and she will rewrite them after the first region goes live.

The support desk

Not a named person, deliberately. Two hour response on a P1 during working hours, four on a P2. Your engineers get the same desk your office staff do, with no separate queue.

03

Slide 3 · checklist · Names four real people rather than a support address, which is the whole point of a handover meeting.

What We Heard, And What We Do Not Know

Taken from the four discovery sessions between May and August, and read back so you can correct it.

What You Told Us

First time fix has sat at 71 percent for three years and the board has asked for 80 by the end of 2027.

Engineers still carry paper job sheets, and about a fifth of them never reach the office in the same week.

Invoicing lags a completed job by eleven working days, which is the single biggest complaint from your finance team.

The 2023 attempt at a field app failed because it was rolled out to all six regions in one weekend.

What We Do Not Know

Whether your asset register is accurate. We have seen the export and roughly a fifth of the records have no site attached.

How your subcontractors will be handled. Forty one of the 240 engineers are not employed by Orrell.

Whether the finance integration can write back on the same day, which depends on a system we have not seen yet.

Who signs off a change to the job sheet once it is live. Nobody in the sales process could name that person.

04

Slide 4 · content · Repeats the sales conversation back so nothing is quietly lost at the handover, and says plainly what is still unknown.

AGREED 28 SEPTEMBER

What This Account Is Judged On

Objective
Key result
Baseline
Status
Fix it first time
First time fix from 71% to 80% by December 2027
71.4%, Aug 2026
Agreed
Get off paper
90% of jobs closed in the app rather than on a sheet
0 of 240 engineers
Agreed
Cut the driving
Median travel per job from 41 minutes to 34
41 min, Aug 2026
Agreed
Invoice faster
Job complete to invoice raised inside 3 working days
11 days, Aug 2026
Agreed
Self service
60% of bookings made by customers, not by your desk
Not measured
Stretch
Baselines measured by Orrell from its own job records for the month of August 2026, not estimated by Tesselate.

05

Slide 5 · metrics · Fixes the four numbers before any work starts, with the baseline written down so the argument cannot be reopened later.

What This Programme Covers And What It Does Not

In Scope

Out Of Scope

Job Scheduling And Dispatch

Mobile App For 240 Engineers

Asset Register Migration

Finance System Integration

Six Regions, Phased

Training And Job Aids

Stock And Van Inventory

Subcontractor Onboarding

Customer Booking Portal

Payroll And Timesheets

Historic Jobs Before 2024

Hardware Procurement

06

Slide 6 · comparison · Puts the exclusions on a slide in the first meeting, which is the cheapest way to prevent a scope argument in month four.

The Ninety Days

Connect

(Oct 2026)

Asset register imported and cleaned with your team. Finance integration built and tested against a copy of your ledger.

One region

(Nov 2026)

North West only, 38 engineers. Paper job sheets keep running beside the app for the whole month.

Prove it

(Dec 2026)

First time fix and travel time compared for North West against the other five. You decide whether to continue.

Go live

(Jan 2027)

Remaining five regions, one a week. Paper retired region by region, only once its engineers stop asking for it.

07

Slide 7 · timeline · The ninety days as four dated milestones, with the region order chosen deliberately rather than alphabetically.

Who Does What

The six activities where a missing owner is what usually delays a go live.

Activity
Orrell
Tesselate
Signed off by
Clean the asset register
Does it
Provides the tooling
Ade Fisher, Ops
Finance integration
Grants access
Builds and tests
Ruth Peel, Finance
Job sheet design
Decides the fields
Builds the form
Ade Fisher, Ops
Engineer training
Releases the time
Runs the sessions
Regional managers
Go or no go, December
Decides
Presents the data
Orrell board
Retiring paper
Decides, per region
Recommends
Regional managers
Anything not on this list defaults to Tesselate. If you think that is wrong, say so today rather than in November.

08

Slide 8 · comparison · A short RACI so the meeting ends with owners rather than goodwill.

What We Need From You

Five items. Every one of them has stalled an onboarding for us before, and every one has a date on it.

Asset register export

A full export including sites, by 10 October, from Ade Fisher.

Finance system access

A read and write test account for your ledger, by 17 October, from Ruth Peel.

A named field champion

One working engineer per region who we can ring at seven in the morning, by 24 October.

Training slots held

Twenty two sessions in the diary before any of them is filled, by 31 October.

A decision maker for the form

One named person who can settle a job sheet argument in a day, by 7 November.

09

Slide 9 · checklist · The five things only the customer can do, each with an owner and a date, which is the real output of a kickoff.

What Engineers Ask

Taken from the first sessions at our other field service customers, in the order they usually come up.

Does it work with no signal?

Yes. The app holds a full day of jobs offline and syncs when it finds a network, and it will not lose a job sheet if the battery dies.

Is it tracking where I am?

Location is recorded at job start and job finish only, never between them, and your regional manager sees the same view you do.

What happens if I get it wrong?

A submitted job sheet can be corrected for seven days by the engineer who raised it, without a supervisor being involved.

Do I have to use my own phone?

No. Orrell is issuing rugged handsets to all 240 engineers before training, and the app is not installed on personal devices.

When does the paper stop?

Not at go live. Paper runs beside the app for a full month in every region, and it is retired only when that region asks.

10

Slide 10 · content · Answers the five questions engineers actually ask, because their objections are what decide adoption.

Start Monday

The asset register export is the only thing blocking week one, and it is due on 10 October.

Success lead

naomi@tesselate.example

Implementation

dev@tesselate.example

Support desk

help@tesselate.example

Next review

30 October, 10am

11

Slide 11 · closing · Ends on four ways to reach the team plus the one date the whole plan hangs on.

The structure

What each slide is doing, so you can reuse the order even with different content.

Slide 1cover
Names the meeting, the date and the go live, so nobody in the room is unclear what is being started.
Slide 2agenda
Shapes a ninety minute kickoff into four parts and says which one is the decision.
Slide 3checklist
Names four real people rather than a support address, which is the whole point of a handover meeting.
Slide 4content
Repeats the sales conversation back so nothing is quietly lost at the handover, and says plainly what is still unknown.
Slide 5metrics
Fixes the four numbers before any work starts, with the baseline written down so the argument cannot be reopened later.
Slide 6comparison
Puts the exclusions on a slide in the first meeting, which is the cheapest way to prevent a scope argument in month four.
Slide 7timeline
The ninety days as four dated milestones, with the region order chosen deliberately rather than alphabetically.
Slide 8comparison
A short RACI so the meeting ends with owners rather than goodwill.
Slide 9checklist
The five things only the customer can do, each with an owner and a date, which is the real output of a kickoff.
Slide 10content
Answers the five questions engineers actually ask, because their objections are what decide adoption.
Slide 11closing
Ends on four ways to reach the team plus the one date the whole plan hangs on.

What makes this deck work

It says what it does not know

The right hand column of slide four lists four open questions, including who signs off a change to the job sheet once it is live. Naming the unknowns at the handover is what stops them becoming a change request in month four.

Baselines are the customer own figures

Every success criterion carries the number Orrell measured from its own job records in August, not an estimate from the vendor. Once the baseline is agreed in the first meeting, the argument about whether anything improved cannot be reopened.

The obligations have owners and dates

Five items the customer has to deliver, each with a named person and a date, and a note that every one of them has stalled an onboarding before. Onboarding rarely fails on the software; it fails on an export nobody sent.

Questions people ask

What should a customer onboarding kickoff deck cover?

Welcome and agenda, the team and escalation path, what was promised in the sales process, success criteria, scope, a phased plan, milestones, roles and responsibilities, what you need from the customer, support arrangements and next steps.

What does a 90 day customer onboarding plan look like?

Four phases in this example: connect and migrate, one region live with the old process running beside it, a measurement gate the customer decides at, then the remaining regions one a week. The gate is the part most plans leave out.

How do you hand off from sales to customer success?

By restating the sales conversation in front of both parties. Slide four of this deck reads back what the customer said across four discovery sessions so it can be corrected, and names the four things the sales process never established.

Why does onboarding matter so much to retention?

Because it is where users decide whether the thing works. Practitioner research consistently ties weak onboarding to early drop off and to churn inside the first quarter, which is why this deck fixes the measurement before the software is touched.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.