Plumbing works contract, 12 Ferndale Street bathroom
Plumbing works contract with a fixture scope table and a compliance certificate
A bathroom job goes over budget in the hour the floor comes up and somebody finds old cast iron drainage. This contract prices every fixture separately, holds a named allowance for what nobody could see, and makes the final payment wait for the compliance certificate.
The document, page by page
Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.
Section by section
What each section is for, so you can keep the ones you need and drop the rest.
- Parties and key terms
- Plumber and owners, the ABN and licence number, the fixed price, allowance and defects period.
- 1. The works
- What is being renovated, the eight row fixture scope table that totals the price, and exclusions.
- 2. Price, contingency and payment
- The fixed price, the $1,200 concealed conditions allowance, the three payment claims and GST.
- 3. Variations and rates
- Changes in writing before the work, and the hourly rates approved variation work is charged at.
- 4. Programme and site
- The dates around the tiler and waterproofer, access, water shutoffs and daily clean up.
- 5. Compliance, defects and insurance
- The compliance certificate, the 12 month defects period, statutory warranties and cover.
- 6. Ending the contract and disputes
- Breach and notice, the QBCC dispute path, governing law and what the contract replaces.
- Signatures
- A block for the plumber carrying its licence number and one for the owners.
Clauses in this document
How to adapt this agreement
For a kitchen rather than a bathroom, swap the fixture rows for sink, dishwasher, fridge water point and gas cooktop connection, and add a gas compliance line if a gas fitter is involved. For a repair call out rather than a renovation, delete the fixed price and the stage table, keep the hourly rates and add a call out fee and a diagnosis step before any work is approved. For a commercial fitout, replace the statutory domestic warranties with a defects liability clause, add a progress claim clause under the state security of payment legislation, and raise the public liability cover to match the head contractor's requirement.
Which law the terms follow
The job is in Queensland, so the compliance certificate is the one a licensed plumber lodges for notifiable work and the licence is a QBCC licence. Statutory warranties for domestic building work under the Queensland Building and Construction Commission Act 1991 apply on top of anything the contract says, and clause 5.2 states that rather than trying to contract around them. Consumer guarantees under the Australian Consumer Law apply to the goods and services and cannot be excluded. GST is added at 10 percent and shown separately on an invoice carrying the ABN and the licence number, and a dispute can go to the Commission before anyone starts proceedings.
What makes this document work
Every fixture carries its own price
Eight rows run from the shower at $1,850 down to fit off and testing at $960, and they add to $11,400 before GST and $12,540 after it. A homeowner deleting the freestanding bath can see exactly what comes off.
Concealed conditions have a budget, not a blank cheque
Clause 2.2 holds $1,200 for failed drainage, unsupported pipework or rot around the old waste, spent only on written approval and not invoiced if unused. That is the difference between a variation and a surprise.
The certificate gates the final payment
Clause 5.1 requires the compliance certificate for the notifiable work within 10 business days and says the final payment is not due until the owner has a copy, so the paperwork arrives with the plumber rather than six months later.
Questions people ask
What should a plumbing contract include?
The scope by fixture, who supplies each item, the fixed price and what it covers, an allowance for what cannot be seen, the payment stages, variation rates, the programme, the compliance certificate, the defects period and insurance. Each of those is a numbered clause here.
What is a plumbing compliance certificate?
It is the certificate a licensed plumber gives for notifiable plumbing work and lodges with the local government. Clause 5.1 requires it within 10 business days of completion and makes the final payment conditional on the owner receiving a copy of it.
Should a plumbing job be fixed price or hourly?
Fixed price for a defined renovation, hourly for repairs. This contract is fixed at $11,400 for the scope in the table, which means an underestimate is the plumber's problem, and it carries a separate hourly rate only for approved variation work.
Who is responsible if the owner supplies the tapware?
The owner. Clause 1.2 marks four fixtures as owner supplied and says the plumber is not responsible for a fault in a fixture it did not supply. The plumber still installs it, still tests it, and still warrants its own installation work for the defects period.
What is a concealed conditions allowance?
A sum held aside for problems that only appear once the wall or floor is opened. Here it is $1,200, spent against the hourly rates, approved in writing before the work starts, and not invoiced at all if it is not needed.
Does a licence number have to be on the contract?
For licensed building and plumbing work in Queensland it belongs there, and it makes the contract easy to check against the public register. This one carries the QBCC licence number in the letterhead, the parties clause, every invoice and the signature block.
Build your own in about a minute
The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.
Make my plumbing works contract with a fixture scope table and a compliance certificateOther document examples
Roofing contract template with a materials table and a weather rule
A roof replacement is the one job where the house is open to the sky at the end of the day, so the clause that matters most is the one about closing it. This contract limits how much roof can be stripped at once, names every product with its warranty years, and says who pays when water gets in.
Electrical contractor agreement with a licence clause and staged payments
Electrical work is the one trade where the paperwork at the end matters as much as the work, because without the certificate the installation is not signed off. This agreement ties the last payment stage to that certificate and sets the progress claim deadlines the payment legislation actually uses.
Cleaning services agreement template with a room by room scope table
Almost every argument about commercial cleaning is an argument about what was in the scope, so this agreement puts the scope in a table with a room, a task list and a frequency on every line. It then settles what a dental practice worries about: who holds the keys, who has been police checked, and what the consumables cost.
Want the steps in the builder? Read Create a document with AI, then Add components to a document. For everything this generator can do, see the document maker.