Electrical contractor agreement, Rye Lane Cafe rewire
Electrical contractor agreement with a licence clause and staged payments
Electrical work is the one trade where the paperwork at the end matters as much as the work, because without the certificate the installation is not signed off. This agreement ties the last payment stage to that certificate and sets the progress claim deadlines the payment legislation actually uses.
The document, page by page
Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.
Section by section
What each section is for, so you can keep the ones you need and drop the rest.
- Cover
- A contract cover naming the job, both companies and the contractor's registration number.
- Parties and key terms
- Legal names, ABNs, the registration number, then the sum, stages and defects period.
- 1. The works
- Scope, the four drawings by revision, exclusions and the licensed work clause.
- 2. Price and payment
- The $38,600 sum, the staged payment table to $42,460 including GST, and progress claims.
- 3. Variations
- Changes in writing before the work, a rate table, and concealed conditions.
- 4. Programme, site and safety
- Dates, the two booked shutdowns, access, and safe work method statements.
- 5. Certificate and handover
- The Certificate of Electrical Safety and the marked up drawings and schedules handed over.
- 6. Defects and warranties
- A 12 month defects period, AS/NZS 3000 compliance and consumer guarantees.
- 7. Insurance, ending and disputes
- Four policies with who holds each, suspension for non payment, termination and adjudication.
- Signatures
- A block for the contractor carrying its registration number and one for the client.
Clauses in this document
- Construction variations clause: directing and pricing changed work
- Defects liability clause: fixing defects after practical completion
- Latent conditions clause: when the ground is not as expected
- Practical completion clause: when the works are ready to use
- Progress claims clause: getting paid as the work advances
- Security of payment clause: working with the state payment laws
- Site access clause: possession, hours and conditions of entry
How to adapt this agreement
For a domestic rewire rather than a commercial fitout, replace the drawing list with a room by room scope, drop the trading hours and shutdown clauses, and add the statutory home building warranties that apply to residential work in your state. For a maintenance arrangement rather than one job, replace the staged payment table with a call out fee and an hourly rate, and swap the defects period for a response time. For a job under the threshold where security of payment does not help, cut clause 2.2 back to a plain 14 day term and keep the rest, because the certificate link in clause 5.1 is doing most of the work.
Which law the terms follow
The agreement sits in Victoria, so the payment clause runs on the Building and Construction Industry Security of Payment Act 2002 and the certificate is the Certificate of Electrical Safety that a registered electrical contractor issues for prescribed work. Safety duties come from the Occupational Health and Safety Act 2004, which is why work at height and live testing each need a safe work method statement before they start. The installation is built to AS/NZS 3000, consumer guarantees under the Australian Consumer Law apply to the goods and services and are not limited, and GST is added at 10 percent on a tax invoice carrying the contractor's ABN and registration number.
What makes this document work
The last payment waits for the certificate
Stage 3, being $11,580 of the $38,600, is not claimable until the Certificate of Electrical Safety is in the client's hands. That one link turns a piece of compliance paperwork into something the contractor has a reason to finish on time.
The payment schedule deadline is in business days
Clause 2.2 gives the client 10 business days to issue a payment schedule and 15 to pay a valid claim. A warning callout explains that staying silent is not a defence, which is the part most people get wrong.
Variations are priced before anyone opens a wall
A four row rate table sets $102 an hour for an electrician, $56 for an apprentice, $153 after hours and materials at cost plus 12 percent, so the concealed conditions clause has real numbers behind it.
Questions people ask
What should an electrical contractor agreement include?
The scope by drawing, who is licensed to do the work, the contract sum and how it is claimed, variation rates, the programme and any shutdowns, safety, the certificate issued on completion, the defects period and insurance. All of those are numbered clauses here.
Does an electrical contract need the licence number in it?
It should. This agreement puts the contractor's registration number on the cover, in clause 1.4, on every invoice and in the signature block, so anyone reading it can check the register. Clause 1.4 also requires the registration to stay current for the whole of the works.
What is a Certificate of Electrical Safety?
It is the document a licensed electrical contractor issues for prescribed electrical installation work, recording the mandatory test results. Clause 5.1 requires it within five business days of completion, and makes the final payment stage conditional on the client holding a copy.
How do staged payments work on an electrical job?
The contract sum is split against milestones anyone can verify. Here it is 30 percent at rough in, 40 percent at fit off and 30 percent at testing and certificate, each claimed by a payment claim rather than invoiced on a date.
What are progress claims under security of payment?
A payment claim states that it is made under the relevant state Act. The party receiving it either pays in full or issues a payment schedule inside the statutory period saying why less is payable. Missing that deadline usually means the claimed amount becomes payable.
Who pays if asbestos is found in the ceiling?
Not the contractor. Clause 3.2 says unsafe existing wiring, asbestos or a structural obstruction stops that part of the work, is reported the same day, and is priced as a variation before anything continues. Asbestos removal is also listed as an exclusion in clause 1.2.
Build your own in about a minute
The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.
Make my electrical contractor agreement with a licence clause and staged paymentsOther document examples
Landscaping contract template with a plant schedule and an establishment period
A garden build is two jobs in one: construction that is finished when it is finished, and planting that is only finished three months later. This contract prices the construction in four stages, lists every plant with its pot size and quantity, and holds the landscaper to a 90 day establishment period for anything that dies.
Plumbing works contract with a fixture scope table and a compliance certificate
A bathroom job goes over budget in the hour the floor comes up and somebody finds old cast iron drainage. This contract prices every fixture separately, holds a named allowance for what nobody could see, and makes the final payment wait for the compliance certificate.
Lawn mowing service agreement for a fortnightly strata round
A mowing round only goes wrong in two places: the week it rains and the week a gate is locked. This agreement prices the whole year as a schedule, says what happens to a visit lost to weather, and puts the gate and the dog in a clause rather than in a text message.
Want the steps in the builder? Read Create a document with AI, then Layout, spacing and page breaks. For everything this generator can do, see the document maker.
Written and checked by the OneCraft team. Last checked .