Common area site inspection report, October 2026, Wexcombe Residences

Site inspection report template with condition ratings and a photo log

A site inspection report has to record what was looked at, what condition it was in, the evidence for that, and who will fix what by when. This four page report by a building manager rates 16 common area items on a four point scale, ties each to its photos, and turns the four poor or unsafe items into six dated defects.

Create a document with OneCraft4 A4 pages, editable, then download as a PDF

The document, page by page

Every page as it renders and as it prints, with nothing summarised. Read the wording before you reuse it.

Wexcombe Residences · Common area inspection SI-2026-10Page 1 of 4
Wexcombe Residences · Common area inspection SI-2026-10Page 2 of 4
Wexcombe Residences · Common area inspection SI-2026-10Page 3 of 4
Wexcombe Residences · Common area inspection SI-2026-10Page 4 of 4
Site inspection report: common areas
Property
Wexcombe Residences, 48 apartments over 8 levels and a basement
Inspection
Thursday 1 October 2026, 9:00 am to 12:15 pm
Inspected by
Rafael Domingo, Building Manager
Reference
SI-2026-10, quarterly common area inspection
Report to
Owners committee, meeting Tuesday 13 October 2026

This is the quarterly walk through of every common area: lobby, lifts, stairwells, corridors, basement car park, bin room, pool and gym, rooftop terrace, fire equipment and gardens. Apartments and balconies are outside its scope. Weather was dry and clear. Sixteen items were rated, 34 photos taken, and six defects raised, two of them urgent and already made safe on the day.

16
Items rated
12
Good or fair
4
Poor or unsafe
6
Defects raised
1. Rating scale
Rating
Meaning
1 Good
Clean, working and in sound repair; no action needed
2 Fair
Wear or a minor fault; fix at the next routine visit
3 Poor
Damaged or not working as intended; repair within 7 days
4 Unsafe
A risk of injury; make safe the same day, repair within 24 hours
2. Items inspected

Photo references match the file names in the inspection folder SI-2026-10. Section 3 lists the photos that show each defect.

Area
Item
Rating
Note
Photos
Lobby
Entry doors and intercom
1 Good
Doors close and latch; intercom tested to apartments 2.04 and 7.01
P01, P02
Lobby
Floor and mailboxes
2 Fair
Two cracked floor tiles by the mailboxes, no lifting edge
P03
Lifts
Lift 1
1 Good
Service tag current, last serviced 14 September
P04
Lifts
Lift 2
2 Fair
Doors slow to close on level 3; logged with the lift contractor
P05
Stairwell A
Treads, rails, lighting
1 Good
All exit signs lit, handrails firm
P06
Stairwell B
Emergency lighting
4 Unsafe
Exit light at level 5 landing not lit; stair dark with power off
P07, P08
Corridors
Carpet, lights, doors
2 Fair
Carpet worn at level 2 lift lobby; two downlights out on level 6
P09, P10
Car park
Floor and bay markings
3 Poor
Cracked slab with a 20 mm lip at bay 31, a trip hazard on the walking route
P11, P12
Car park
Roller door and lights
1 Good
Door opens on fob and stops on the safety beam
P13
Bin room
Bins and ventilation
2 Fair
Recycling bins overfull on Thursday; extraction fan working
P14
Pool
Pool fence and gate
4 Unsafe
Gate does not self close from 30 degrees open; latch missed twice
P15, P16
Pool
Water and plant room
1 Good
Daily log complete; plant room locked
P17
Gym
Equipment and floor
1 Good
Equipment wiped down; rower serviced in August
P18
Roof terrace
Balustrade and furniture
3 Poor
Glass panel 6 loose in its channel by about 5 mm; no crack
P19 to P21
Fire equipment
Extinguishers and hose reels
1 Good
All 18 tags current; hose reels on levels 1 to 8 present
P22 to P29
Gardens
Paths and irrigation
1 Good
Paths clear; irrigation timer checked against the schedule
P30 to P34
3. Photo log

Thirty four photos were taken on a phone with the date and time stamped, and saved to the shared inspection folder the same afternoon. The photos that show a defect are listed here so the committee and contractors can find them without opening the whole set.

Photo
Location
What it shows
P07, P08
Stairwell B, level 5
Exit light unlit, then the landing with the test switch off
P11, P12
Car park, bay 31
Cracked slab, with a ruler showing the 20 mm lip
P15, P16
Pool gate
Gate held at 30 degrees, then resting unlatched
P19 to P21
Roof terrace, panel 6
Panel movement in the channel, and the gap at the top fixing
P03
Lobby
Two cracked tiles beside the mailboxes
P09, P10
Level 2 and level 6
Worn carpet at the lift lobby; two failed downlights
4. Defects and follow up

Each defect has a priority from the rating scale, the action taken or needed, the contractor and a due date. Urgent items were made safe before leaving site.

No.
Defect
Priority
Action
Who and when
D1
Stairwell B exit light, level 5
Urgent
Portable light placed on the landing; fitting to be replaced
Electrician, Fri 2 Oct 2026
D2
Pool gate not self closing
Urgent
Pool closed and gate chained; hinge spring to be replaced
Fencing contractor, Fri 2 Oct 2026
D3
Car park slab, bay 31
Poor
Coned off; grind the lip and patch the crack
Concrete contractor, Thu 8 Oct 2026
D4
Roof terrace glass panel 6
Poor
Terrace furniture moved back; reset the panel and check all 14
Glazier, Thu 8 Oct 2026
D5
Lift 2 doors slow, level 3
Fair
Adjust at the October service
Lift contractor, Wed 14 Oct 2026
D6
Downlights, tiles, carpet
Fair
Replace downlights; quote tiles and carpet for the committee
Building Manager, Fri 30 Oct 2026
No.
Defect
Priority
Action
Who and when
D1
Stairwell B exit light, level 5
Urgent
Portable light placed on the landing; fitting to be replaced
Electrician, Fri 2 Oct 2026
D2
Pool gate not self closing
Urgent
Pool closed and gate chained; hinge spring to be replaced
Fencing contractor, Fri 2 Oct 2026
D3
Car park slab, bay 31
Poor
Coned off; grind the lip and patch the crack
Concrete contractor, Thu 8 Oct 2026
D4
Roof terrace glass panel 6
Poor
Terrace furniture moved back; reset the panel and check all 14
Glazier, Thu 8 Oct 2026
D5
Lift 2 doors slow, level 3
Fair
Adjust at the October service
Lift contractor, Wed 14 Oct 2026
D6
Downlights, tiles, carpet
Fair
Replace downlights; quote tiles and carpet for the committee
Building Manager, Fri 30 Oct 2026
No.
Defect
Priority
Action
Who and when
D1
Stairwell B exit light, level 5
Urgent
Portable light placed on the landing; fitting to be replaced
Electrician, Fri 2 Oct 2026
D2
Pool gate not self closing
Urgent
Pool closed and gate chained; hinge spring to be replaced
Fencing contractor, Fri 2 Oct 2026
D3
Car park slab, bay 31
Poor
Coned off; grind the lip and patch the crack
Concrete contractor, Thu 8 Oct 2026
D4
Roof terrace glass panel 6
Poor
Terrace furniture moved back; reset the panel and check all 14
Glazier, Thu 8 Oct 2026
D5
Lift 2 doors slow, level 3
Fair
Adjust at the October service
Lift contractor, Wed 14 Oct 2026
D6
Downlights, tiles, carpet
Fair
Replace downlights; quote tiles and carpet for the committee
Building Manager, Fri 30 Oct 2026
Pool closed until the gate is fixed
A notice went to all residents at 12:30 pm on 1 October. The pool reopens only after the gate has been tested to close and latch from every open position, and the test is recorded in the pool log.
5. Since the last inspection

All seven defects from the July inspection are closed except one: the level 2 carpet, which the committee deferred to this quarter and which is now quoted under D6. Two of this quarter's defects, the stairwell light and the pool gate, were not present in July, so the next inspection will add a monthly test of both between quarterly walks.

I inspected the areas listed on the date stated, and this report and its ratings are an accurate record of what I saw. The next quarterly inspection is booked for Thursday 7 January 2027.

Building Manager
Name
:
Rafael Domingo
Date
:

Section by section

What each section is for, so you can keep the ones you need and drop the rest.

Inspection details
Property, date and time, inspector, reference and the committee the report goes to.
Scope and headline figures
Areas covered and excluded, weather, and counts of items, ratings and defects.
1. Rating scale
Four ratings from Good to Unsafe with the response time each sets.
2. Items inspected
Sixteen items by area with rating, note and photo references.
3. Photo log
The photos that show a defect, with location and what each shows.
4. Defects and follow up
Six defects with priority, action, contractor and due date, and the pool closure notice.
5. Since the last inspection
Status of last quarter's defects, the next date, and the inspector's signature.

How to adapt this document

First, for a construction site visit rather than a finished building, replace the areas with work zones and add columns for the trade responsible and whether the work matches the drawings, keeping the rating scale. Second, for a rental property inspection at the start or end of a lease, rate each room instead of common areas and have both parties sign, because the report becomes evidence about the bond. Third, if you inspect monthly, drop the photo log and keep only the defects table, carrying open items forward until they close.

What makes this document work

The rating scale sets the response time

Each rating carries its own deadline: Poor means repair within 7 days, Unsafe means make safe the same day and repair within 24 hours. So when the pool gate and the stairwell light are rated 4 Unsafe, nobody has to argue about how fast to move.

Every finding points to its evidence

The items table gives photo references for all 16 items, and the photo log describes the ones that matter, such as P11 and P12 showing the bay 31 slab with a ruler on the 20 mm lip. A contractor can quote from the photo before visiting.

It closes the loop on last quarter

Section 5 reports that six of seven July defects are closed and the seventh, the level 2 carpet, is now quoted. It also notes the two urgent defects are new and adds a monthly test of both, which is how an inspection regime improves itself.

Questions people ask

How often should common areas be inspected?

Quarterly walk throughs are common for apartment buildings, with some items checked more often: fire doors, exit lights and pool gates are often tested monthly, and fire equipment on the schedule set by the relevant standard. The owners or their manager set the frequency, and local law may set minimums for fire safety and pools.

Should the inspector fix problems on the day?

Anything that could hurt someone should be made safe before the inspector leaves, even if the repair comes later. Here the pool was closed and its gate chained, the stair landing given a portable light, and the car park lip coned off. Making safe is a temporary control; the report still needs a dated repair.

How many photos should an inspection report include?

Take enough to show the condition of every item, and at least one close and one wide photo of each defect, with something for scale. Keep the full set in a dated folder and list only the defect photos in the report. A report full of embedded pictures is hard to read and slow to send.

Who should sign a site inspection report?

The person who did the inspection, confirming that the report records what they saw on that date. Here the building manager signs alone. Where a contractor or engineer inspects a specialist item, such as a lift or balustrade, they issue their own report or certificate, and this report refers to it rather than repeating it.

What is the difference between a site inspection and a building condition report?

A routine site inspection checks the day to day condition and safety of what people use, and turns faults into repairs. A building condition report is a deeper, less frequent assessment, usually by an engineer or surveyor, of structure, roofs, services and remaining life, often to plan long term maintenance funding.

Can residents see the inspection report?

That depends on the building's rules and who commissioned the report. Owners committees often share a summary, especially when an amenity such as the pool is closed. If the report is shared, remove anything personal, such as which apartment reported a problem, and keep the defect list and dates, which is what residents want to know.

Build your own in about a minute

The button below opens the generator with this use case already described. Change the wording to match your own, generate, then edit anything you like.

Make one like this

Other document examples

Want the steps in the builder? Read Create a document with AI, then Document builder components. For everything this generator can do, see the document maker.

Sources

Written and checked by the OneCraft team. Last checked .